After a cold fall, it has warmed back up a bit out here.  We have been getting a few hours of work done nearly everyday at the crib.  The highlights include:

  • The front bin has been removed.
  • Fresh sub-floor covering the greenhouse sides, the front bin, and the opposite side up to where the stairs are planned.
  • Bunch of structural repairs and reinforcements
  • Two lost windows covered with plywood for the winter
  • Still trying to evict the pigeons.
  • A new pit cover in the greenhouse.

I want/hope to make a big swoop of progress to finish up a bit this weekend, and get some pictures taken again.  The next big steps will be:

  • Framing for windows on the front wall.  Probably install them in the Spring anyway
  • A Staircase!
  • Electrical on the 2nd floor.  An outlet or two will be better then these extension cords.
  • Cover that last window.
  • Add solid sheathing between greenhouse and ‘house’

The size and shape of the main room has really become apparent.  It looks pretty cool.  All this floor to walk around on - amazing.  What else could you do up here?